PRJ-MCIA-T2-EXPDemo Purpose • Sample PricesBudget Healthy (<80%)Created: 2026-08-20

Mactan-Cebu International Airport (MCIA) T2 Expansion CCTV & Video Wall

GMR-Megawide Cebu Airport Corporation (GMCAC)
Lapu-Lapu City, Cebu
2026-09-15 2026-12-30

45 Axis 4K Panoramic Cameras, Milestone XProtect VMS Server, and 3x3 55-inch Barco Video Wall matrix in Airport Security Operations Center (SOC).

Field Note: Site survey completed. Submitting technical shop drawings for GMCAC engineering approval.
Status:
Contract Value₱7,200,000.00Agreed Client Price
Expense Budget₱5,100,000.00Allocated Cap
Actual Spent0.0%
₱0.00
Remaining Funds₱5,100,000.00Available
Gross Margin100.0%₱7.20M profit
Client Paid₱0.00of ₱2.16M
Camera → Operator Phases
2 items

End-to-End Installation Milestones (Camera → Operator)

Track phase completion, physical progress, and phase-linked cost drawdowns.

PHASE 1

Phase 1: Engineering Survey & Architectural Shop Drawings

IN_PROGRESS

CAD overlays, 3D line-of-sight studies, and GMCAC permit signoffs.

Allocated Budget: ₱350,000.00Phase Cost Incurred: ₱0.00 (0.0%)Variance: ₱350,000.00
Progress80%
PHASE 2

Phase 2: Cable Trays, Conduiting & CAT6A STP Network Runs

PENDING

Terminal 2 expansion wing cable routing.

Allocated Budget: ₱1,400,000.00Phase Cost Incurred: ₱0.00 (0.0%)Variance: ₱1,400,000.00
Progress0%